28 de abril de 2008

Millions in Iraq contracts never finished

Millions of dollars of lucrative Iraq reconstruction contracts were never finished because of excessive delays, poor performance or other factors, including failed projects that are being falsely described by the U.S. government as complete, federal investigators say.

The audit released Sunday by Stuart Bowen Jr., the special inspector general for Iraq reconstruction, provides the latest snapshot of an uneven reconstruction effort that has cost U.S. taxpayers more than $100 billion. It also comes as several lawmakers have said they want the Iraqis to pick up more of the cost of reconstruction.

The special IG's review of 47,321 reconstruction projects worth billions of dollars found that at least 855 contracts were terminated by U.S. officials before their completion, primarily because of unforeseen factors such as violence and excessive costs. About 112 of those agreements were ended specifically because of the contractors' actual or anticipated poor performance.

In addition, the audit said many reconstruction projects were being described as complete or otherwise successful when they were not. In one case, the U.S. Agency for International Development contracted with Bechtel Corp. in 2004 to construct a $50 million children's hospital in Basra, only to "essentially terminate" the project in 2006 because of monthslong delays.

But rather than terminate the project, U.S. officials modified the contract to change the scope of the work. As a result, a U.S. database of Iraq reconstruction contracts shows the project as complete "when in fact the hospital was only 35 percent complete when work was stopped," said investigators in describing the practice of "descoping" as frequent.

"Descoping is an appropriate process but does mask problem projects to the extent they occur," the audit states.

The report paints a depressing picture of money being poured into failed Iraq reconstruction projects — contractors are killed, projects are blown up just before being completed, or the contractor just stops doing the work.

No hay comentarios.:

Publicar un comentario